Small Projects

Project undertaken in Febuary 2011 completed 31 March 2011

To remove the existing kitchen, new ceiling with insulation and down lights. Replaster all walls, redo the plumbing, supply and install new high gloss white cupboards, install a new floor, glass splash backs and decorate.

Extremely nice clients, very patient. We remodelled their bathroom three years ago, Kingston Upon Thames.

Stripping. Always a messy job. Plumbing. Easy to sort out. Dizzy floor. Lets get rid of it.
Lowered ceiling to allow insulation. All hands on deck. I think I know how to do that. Wow. Finished already?
The truth. Eight weeks to complete. Between the building work. The ten day delay for the granite.
Glass splash backs can only be measured after granite installation. Final clean ups and adjustments. A very nice and trendy kitchen.
Client happy to see the back of us. We did not create the view. A job like this should not be measured in time of installation but by its beauty. Complete 31/03/2011

    

                                                                                   